Aptitude Questions

==>> A and B can do a piece of work in 12 days ; B and C can do it in 20 days. In how many days will A, B and C finishes it working all together?

Also, find the number of days taken by each to finish it working alone?

Ans:60 days

Sol: (A+B)’s one day’s work=1/12; (B+C)’s one day’s work=1/15 and (A+C)’s one day’s
work=1/20.
Adding, we get: 2(A+B+C)’s one day’s work = (1/12+1/15+1/20)=1/5.
Therefore, (A+B+C)’s one day’s work=1/10.
Thus, A, B and C together can finish the work in 10 days.
Now, A’s one day’s work
= [(A+B+C)’s one day’s work] – [(B+C)’s one day’s work]
= 1/10-1/15)
= 1/30.
Therefore, A alone can finish the work in 30 days.
Similarly, B’s 1 day’s work = (1/10 -1/20) = 1/20.
Therefore, B alone can finish the work in 20 days.
And, C’s 1 day’s work= (1/10-1/12) = 1/60.
Therefore, C alone can finish the work in 60 days.

==>> A is twice as good a workman as B and together they finish a piece of work in 18
days.In how many days will A alone finish the work?

Ans:27 days.

Sol: (A’s 1 day’s work): (B’s 1 day’s work) = 2:1.
(A + B)’s 1 day’s work = 1/18.
Divide 1/18 in the ratio 2:1.
Therefore A’s 1 day’s work = (1/18 * 2/3) = 1/27.
Hence, A alone can finish the work in 27 days.

==>> 2 men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can do the same work in 8 days. In how many days can 2 men and 1 boy do the work?

Ans: 12 ½ days.

Sol: Let 1 man’s 1 day’s work = x and 1 boy’s 1 day’s work =y.
Then, 2x+3y=1/10 and 3x+2y=1/8.
Solving, we get: x=7/200 and y=1/100.
Therefore (2 men +1 boy)’s 1 day’s work = (2*7/200 + 1*1/100) = 16/200 = 2/25.
So, 2 men and 1 boy together can finish the work in 25/2 =12 ½ days.